On June 13, 2024, the Federal Energy Regulatory Commission (FERC) issued an “Order to Show Cause”[1] (Order) under Section 206 of the Federal Power Act to four regional transmission organizations (RTOs) and independent system operators (ISOs). FERC is concerned that the RTOs/ISOs’ open access transmission tariffs (OATT) are unjust, unreasonable, and discriminatory because they allow transmission owners (TOs) to unilaterally elect “TO Initial Funding” (a funding mechanism that allows TOs to fund network upgrade capital costs upfront and then recover those costs from interconnection customers) which FERC believes may create barriers to interconnection and result in discrimination.

FERC is directing the Regional Transmission Operators (RTOs) and Independent System Operators (ISOs) to either show cause as to why their OATTs are just and reasonable or explain what changes they would make to remedy the concerns. The Order acknowledges and discusses the background of the issue, including FERC’s Order No. 2003, which established an interconnection pricing policy that allows RTOs/ISOs to propose alternative pricing mechanisms.

However, FERC is concerned about the potential for discrimination when the transmission provider is not independent. The Order further discusses the different ways that network upgrade costs can be funded in the Midcontinent Independent System Operator (MISO) region, recent case history related to TO Initial Funding, and a number of proceedings related to the issue. The Order also raises concerns about potential discrimination by transmission owners in PJM, Southwest Power Pool (SPP), and ISO New England, as well as questions about whether transmission owners face any uncompensated risks associated with owning, operating, and maintaining network upgrades.

FERC requests the RTOs/ISOs to address these concerns and answer a number of questions related to increased costs and potential discrimination.  Under its Section 206 authority, FERC directs each of the four RTOs/ISOs, within 90 days of the date of the Order (i.e., Wednesday, September 11, 2024), either: (1) to show cause as to why its OATT remains just and reasonable and not unduly discriminatory or preferential and provide responses to the questions set forth in the Order; or (2) to explain what changes to its OATT it believes would remedy the identified concerns if the commission does determine the self funding to be unjust and unreasonable.

The impact of “TO self funding” on generation developers can be substantial. Here is a breakdown of the potential impacts on generation developers:

  • Increased Costs: When transmission owners can pass on the upfront capital costs of network upgrades to generation developers, it significantly increases the cost of connecting to the grid, impacting the financial viability of new generation projects.
  • Barrier to Entry: These additional costs serve as a barrier to entry, particularly for smaller developers or those with more innovative or less capital-intensive technology, impacting resource diversity and competitiveness of the market.
  • Project Delays: Disputes over cost allocations and the process of funding network upgrades lead to project delays, harming generation developers who rely on predictable timelines to plan and execute their projects and secure financing.
  • Financing Challenges: The uncertainty and potential for increased costs associated with network upgrades make it more difficult for generation developers to secure financing, as lenders and investors may see the projects as riskier investments.
  • Operational Risks: Questions raised by FERC about whether transmission owners face any uncompensated risks associated with owning, operating, and maintaining network upgrades might affect terms and conditions of interconnections, potentially passing more risks onto generation developers.
  • Discrimination Concerns: The potential for discriminatory practices by transmission owners could undermine the fair and competitive access to the grid for new generation developers, potentially favoring incumbent players or certain types of generation.

The FERC directive for RTO/ISOs to either justify the fairness of these practices or propose changes is therefore very significant for generation developers, who stand to benefit if the costs and risks associated with network upgrades are distributed more equitably and transparently.

For more information about the Order’s potential impact on your specific situation or to explore the next steps in light of the Order, please contact Michael Blackwell or a member of Husch Blackwell’s Energy Regulation team.


[1] Midcontinent Indep. Sys. Operator, Inc., et al., 187 FERC ¶ 61,170 (2024) (FERC Docket Nos. EL24-80-000, EL24-81-000, EL24-82-000, EL24-83-000).

Last month, Husch Blackwell published its seventh-annual report on public-private partnerships (P3s) and alternative project delivery strategies. This year’s report features an interesting article by Michael Blackwell, an attorney on the firm’s Energy & Natural Resources team, that explores how P3s and P3-like agreements might be deployed to hasten the transition from fossil fuels

At its May 13, 2024 open meeting the Federal Energy Regulatory Commission (FERC) unanimously approved Order No. 1977,[1] which updates the process FERC uses when exercising its transmission siting authority under Section 216 of the Federal Power Act, as amended by the Infrastructure Investment and Jobs Act of 2021 (IIJA). 

At its May 13, 2024 open meeting, the Federal Energy Regulatory Commission (FERC) approved a groundbreaking final rule—Order No. 1920[1] —requiring public utilities to undertake new long-term regional transmission planning over a 20-year horizon and allocate the cost of selected transmission projects in a manner that corresponds to the benefits they provide. 

On May 29, 2024, the U.S. Treasury Department and the Internal Revenue Service issued a notice of proposed rulemaking (“NPRM”) that includes guidance on two of the Inflation Reduction Act of 2022’s renewable electricity tax credits – but which notably failed to provide guidance with respect to the eligibility of clean electricity generated by biogas or renewable natural gas (“RNG”) for those credits, leaving RNG developers with lingering questions. 

On April 30, 2024, the Department of the Treasury issued final regulations on tax credit transfers that allow hydrogen producers to sell tax credits earned under § 45V of the Inflation Reduction Act (IRA). Section 6418 of the Internal Revenue Code and the final regulation issued thereunder allow credit purchasers to use purchased credits to offset their tax liability. Credit sellers will be able to sell credits that they would not otherwise be able to use due to insufficient tax liability. Given such powerful incentives, many energy producers are wondering how to add “green” hydrogen (discussed below) to their portfolios by powering hydrogen facilities with wind turbines and solar panels. Here, we discuss what wind and solar producers should keep in mind as they plan, negotiate, and begin developing hydrogen plants powered by renewable energy, with a particular focus on site control.

NERC recently filed rule changes with FERC that propose to significantly expand NERC registration and compliance requirements to inverter based resources, such as renewable energy and battery facilities, that historically were too small to be subject to such requirements.  NERC’s proposed rule changes are one of the latest developments in NERC’s multi-year effort to address the “reliability gap” associated with these types of resources.

As the energy transition continues, battery energy storage has become an increasingly critical form of technology to support and maximize variable renewable energy resources such as wind and solar, and add a level of reliability and resilience to the grid. While the development process for a standalone battery energy storage project typically does not differ significantly from its wind or solar counterparts, there are a several considerations unique to the nature of battery storage to consider when negotiating the site control documents for the project.